Clerk of works requirements typically involve on-site monitoring, gathering of supporting information (time sheets, equipment counts, etc.), and confirming that invoicing is relevant and free of duplication. Whether the contractual arrangements are Time & Material (T&M), Cost-Plus (CP), Guaranteed Maximum Price (GMP), or Integrated Project Delivery (IPD), the typical accountant’s contributions to a project are limited and measurable.
An experienced forensic accountant, with a comprehensive understanding of construction scope and terminology, industry standards and issues, and tricks-of-the-trade, can serve as the eyes and ears of the adjuster and/or project owner. The days of simply gathering and verifying supporting documentation are no longer.
Whether it is labor, equipment, materials and reimbursable expenses, soft costs, or markups and taxes, forensic procedures can be applied to identify:
Inefficiencies
Excessive spending and billing
Duplication and unrelated costs
Departures from contractual agreements and scope
Inconsistencies with industry standards
Fraud and abuse
The value of an experienced forensic accountant can begin prior to the commencement of work. A clerk of works site inspection can identify and value the implications of proposed contractual terms and set a successful course through to the completion of a construction or reconstruction project. Whether intentional or unintentional, a general contractor and/or the subcontractors may significantly overestimate and/or overbill the project owner.
The forensic accountants are able to provide an unbiased, independent analysis, with the understanding that the relationship between the project owner and general contractor must often continue beyond the completion of our involvement. The highly technical expertise, in conjunction with heavily trained soft skills, fosters an environment of cooperation between the parties involved and drives projects to efficient and equitable outcomes.
Following Hurricane Katrina, for one project in New Orleans alone, between the stabilization and reconstruction invoicing, Meaden & Moore’s professionals had findings nearing $30 million. Included in our findings were:
Inflated labor hours
Ghost employees
Overtime charges that were not in accordance with how they were being paid
Excessive supervisor-to-laborer ratios
Labor charges for overhead classifications
Charges for monitored inefficient labor
Excessive equipment usage charges and consumables charges
Consumables charges duplicated with reimbursable charges
Duplicated and unrelated reimbursable charges and mobilization/demobilization charges
Unrelated and inaccurate general conditions charges
Compounding and inappropriate overhead and profit mark-ups
Inappropriate tax mark-ups.
These findings were tangible and measurable. What wasn’t measurable was how much was inherently saved simply due to our on-site presence, monitoring, and active participation and communication with the parties involved during the course of the project.
With a wealth of knowledge in construction scope, terminology, industry standards, and industry issues, obtained through vast experience in all construction settings, Meaden & Moore’s professionals possess the tools to provide a clerk of works site inspection that goes beyond the numbers. Our partnership with our clients, hands-on implementation of processes, and collaboration with the involved parties delivers cost-effective and equitable resolutions to the insurance loss and design and build sectors.